Ohio’s Tougher Power and Zoning Rules Are Good for Serious Developers

by Adnan Zai | November 20, 2026 | Cleveland, Data Centers

There is a lot of talk right now that Ohio has turned cold on data centers. Utilities want more money up front. Townships are passing moratoriums. Voters just said no in town after town.

We see it differently. Ohio is not closing the door. It is checking who is serious before letting them in, and that is good news for anyone who actually intends to build.

The Queue Needed a Trim

Start with the numbers. In 2024, AEP Ohio reported requests to connect more than 30,000 megawatts of data center load, according to testimony from Jenifer French, chair of the Public Utilities Commission of Ohio (PUCO), to the legislature’s Select Committee on Data Centers in May 2026. Once the utility’s new data center tariff was in place, it signed agreements for 5,642 megawatts.

Some read that drop as a market falling apart. We read it as a market cleaning house. French told lawmakers it was hard for AEP Ohio to tell how much of the 30,000 megawatts was real and how much was speculative. Critics, including the Ohio Manufacturers’ Association, argue the figure was never well supported. Either way, a queue packed with placeholders hurts the real projects stuck behind them. When roughly four out of five requests fall away the moment someone asks for a financial commitment, many of them were not projects. They were options on somebody else’s grid.

Power Has to Be Paid For

The AEP Ohio data center tariff is simple in concept. A new data center of 25 megawatts or more reserves a block of capacity and pays a minimum charge on up to 85 percent of it, whether it uses the power or not. Contracts run up to 12 years, including a ramp-up period of as long as four. The customer posts collateral, and leaving early can cost 36 months of minimum charges.

We have no problem with any of that. Lenders expect firm commitments before they fund a building, and a utility should expect the same before it builds a substation. If a project cannot carry those terms, it was unlikely to be built anyway. Better to learn that before closing on the land than after.

The same discipline applies to the site itself. A transmission line along the property line is not a power plan. That line may already be full, and serving a large new load can require a new substation or upgrades miles away. What matters is a written commitment from the utility.

FirstEnergy and AES Ohio are next. French told lawmakers the commission had directed FirstEnergy to propose its own data center tariff, and that commission staff had recommended one in AES Ohio’s rate case. The details are still open, but we would expect the final terms to follow AEP Ohio’s lead.

Towns Have a Right to Ask

At least 138 Ohio municipalities and townships had active data center moratoriums as of September 17, 2026. In this month’s election, residents of 18 Ohio communities voted on 21 data center measures, and in every one of them voters chose to restrict or ban data centers. A statewide campaign is now collecting signatures to put a moratorium before all Ohio voters.

We are not going to fault a township for wanting rules before it approves a building that runs around the clock next to farms and subdivisions. A good moratorium buys time to write a code on noise, setbacks, power infrastructure and distance from homes. Our concern is whether the pause ends with a code someone can actually build to.

The industry owns part of this, too. When a project arrives under a code name and the neighbors hear about it last, no one should be surprised by the vote.

What We Check Before a Land Deal Moves Forward

The list is short, and none of it gets skipped.

First, power. The utility’s answer should be in writing: how many megawatts, from which substation and by when.

Second, cost. If the site needs a substation or transmission work, we want to know who pays and what that does to the returns. Under tariffs like AEP Ohio’s, the minimum charges and collateral belong in the model on day one.

Third, zoning. Is a data center permitted by right, allowed only with conditional use approval, or not mentioned at all? Silence in the code is not permission. These days it usually means a fight is coming.

Fourth, the local mood. That means reading the township minutes and checking for proposed amendments and ballot petitions before anyone signs, not after.

Finally, the clock. Utility studies, permits and construction move at physical speed, and the slowest one sets the schedule. The purchase contract should be built around that schedule, with contingencies and extensions where the seller will agree to them.

Ohio Still Works for the Prepared

We still like Ohio. The state has about 200 data centers, the fifth most in the country, and the reasons they came here have not gone anywhere.

What has changed is the order of operations. Power and zoning used to come after price and acreage. Now they come first. Firmer utility commitments push out the speculators, and clearer local rules tell a buyer what can be built before the money moves. Both make the work easier.

In Ohio today, the land is the easiest part of a data center deal to secure. Power and local approval decide whether it closes.

Sources

  1. Public Utilities Commission of Ohio, Chair Jenifer French, comments before the Select Committee on Data Centers, May 27, 2026. https://search-prod.lis.state.oh.us/api/v2/general_assembly_136/committees/cmte_h_data_centers_1/meetings/cmte_h_data_centers_1_2026-05-27-1000_1337/submissions/pucochairfrenchcommentsbeforetheselectcommitteeondatacenters(2)05.27.2026.pdf
  2. AEP Ohio, Data Center Tariff (Schedule DCT) summary, accessed November 18, 2026. https://www.aepohio.com/company/about/rates/data-center-tariff
  3. Ohio Capital Journal via Highland County Press, “AEP Ohio says new data center tariff is working, critics aren’t buying it,” February 2026. https://highlandcountypress.com/headlines/aep-ohio-says-new-data-center-tariff-working-critics-arent-buying-it
  4. Ohio Capital Journal, “Ohio now has over 125 active moratoriums on data centers,” September 18, 2026. The article reports at least 138 as of September 17. https://www.newsfromthestates.com/node/428178
  5. Fortune, “Ohio data center ballot measures,” November 4, 2026. https://fortune.com/2026/11/04/ohio-data-center-ballot-measures-midterm-elections/
  6. Ohio Capital Journal, “Data centers go 0-for-21 in ballot initiatives around Ohio,” November 9, 2026. https://www.newsfromthestates.com/node/437398
  7. Ohio Capital Journal via Highland County Press, “Ohio data center ban advocates are trying to get 413,000 signatures by July 1,” 2026. https://www.highlandcountypress.com/headlines/ohio-data-center-ban-advocates-are-trying-get-413000-signatures-july-1
  8. Office of the Ohio Consumers’ Counsel, “Quick Facts: Data Centers in Ohio.” https://occ.ohio.gov/factsheet/data-centers